Heading: |
National Grid |
Question ID: |
1817831 |
UIN: |
63804 |
House: |
Commons |
Date tabled: |
2025-06-30 |
Asking Member ID: |
5316 |
Asking Member display name: |
Mike Reader
|
Asking Member handle: |
mike_reader
|
Asking Member Twitter reference: |
@mike_reader
|
Member interest: |
false |
Question text: |
To ask the Secretary of State for Energy Security and Net Zero, if he will hold discussions with Ofgem on reducing the time taken to implement reforms to the electricity distribution network. |
Is named day: |
false |
Date of holding answer: |
|
Date answered: |
2025-07-08 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
4998 |
Answering Member display name: |
Michael Shanks
|
Answering Member handle: |
mgshanks
|
Answering Member Twitter reference: |
@mgshanks
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
The National Infrastructure Commission published recommendations on 21 February on making the electricity distribution network fit for net zero. The Government published a formal response on 7th July, which agrees with the study’s view that investment in ... |
Original answer text: |
|
Comparable answer text: |
|
Answering body ID: |
215 |
Answering body name: |
Department for Energy Security and Net Zero |
Tweeted: |
true |