Heading: |
Project Gigabit: North Shropshire |
Question ID: |
1807108 |
UIN: |
55519 |
House: |
Commons |
Date tabled: |
2025-05-30 |
Asking Member ID: |
4934 |
Asking Member display name: |
Helen Morgan
|
Asking Member handle: |
helenmorganmp
|
Asking Member Twitter reference: |
@helenmorganmp
|
Member interest: |
false |
Question text: |
To ask the Secretary of State for Science, Innovation and Technology, what assessment he has made of the progress of the Project Gigabit rollout in North Shropshire constituency since 1 January 2025. |
Is named day: |
true |
Date of holding answer: |
|
Date answered: |
2025-06-04 |
Date answer corrected: |
|
Is holding answer: |
false |
Is correcting answer: |
false |
Answering Member ID: |
1446 |
Answering Member display name: |
Chris Bryant
|
Answering Member handle: |
|
Answering Member Twitter reference: |
Chris Bryant
|
Correcting Member ID: |
|
Correcting Member display name: |
|
Correcting Member handle: |
|
Correcting Member Twitter reference: |
|
Answer text: |
As part of Project Gigabit, Freedom Fibre was awarded a contract to deliver gigabit-capable broadband to premises in North Shropshire that were not expected to be reached by suppliers’ commercial rollout.As of 1 May 2025, Building Digital UK (BDUK) had re... |
Original answer text: |
|
Comparable answer text: |
|
Answering body ID: |
216 |
Answering body name: |
Department for Science, Innovation and Technology |
Tweeted: |
true |